RIVIERE DES GALET AND SOUILLAC
- RESPONSIBLE OF A TEAM OF SUPERVISION AND DRAFTSMAN
2012 - 2013
RESPONSIBLE OF A TEAM FOR SUPERVISION OF REHABILITATION OF THREE STEEL BRIDGE (TAMARIN, RIVIERE DES GALET AND SOUILLAC) REPLACE DAMAGES STRUCTURE, BOLTS, NETS, PAINTING, ENLARGE THE BRIDGE BY 1.2M.AND COMMISSIONING FOR (ROAD DEVELOPMENT AUTORIT,
-
SAVANNAH, MAURITIUS
- RESPONSIBLE OF A TEAM OF SUPERVISION AND DRAFTSMAN
2006 - 2007
WORK FOR THE CONSTRUCTION OF A NEW COOLING TOWER AND PIPING FOR AIR, SERVICE ,AIR INSTRUMENTATION ,WATER SERVICE, DEMIN WATER AND CONDENSATE WATER AT CTSAV (SAVANNAH, MAURITIUS) FOR THE MECHANICAL SERVICES:
-
MECHANICAL SERVICES
- RESPONSIBLE OF A TEAM OF SUPERVISION AND DRAFTSMAN
2005 - 2005
WORK FOR THE CONSTRUCTION OF A NEW COOLING TOWER CTDS (UNION ST AUBAIN, MAURITIUS) FOR THE
-
NEW POWER PLANT AT CTSAV
- DRAFTING WORK FOR THE CONSTRUCTION OF BELT CONVEYOR
2005 - 2005
FOR NEW POWER PLANT AT CTSAV (SAVANNAH, MAURITIUS) FOR THE MECHANICAL SERVICES
-
MAINTENANCE AT REUNION
- RESPONSIBLE OF A TEAM OF SUPERVISION
2004 - 2004
MAINTENANCE AT REUNION ISLAND AT CTBR ON GEARBOXES, ALTERNATOR 32 MW, MISSES ALIMENT AND RESET ALIMENT UP TO 0,02MM
-
HOTEL UPGRADING ALL
- RESPONSIBLE OF A TEAM OF SUPERVISION AND DRAFTSMAN
2003 - 2003
MAINTENANCE AT VICTORIA HOTEL UPGRADING ALL DISTRIBUTION WATER PUMPS, INSTALLATION OF NEW CHILLER, INSTALLATION OF HOT WATER PUMPS, DESIGN AND IMPLEMENTATION OF NEW PIPING TO FIT NEW PUMPING INSTALLATION
-
ALCODIS ROSE BELLE
- INSTALLATION
2003 - 2003
INSTALLATION OF TURBINE AND ALTERNATOR 1.5 MW, BELT CONVEYOR, AND DESIGN AND
-
MAINTENANCE AT LEMURIA HOTEL
- RESPONSIBLE OF A TEAM OF SUPERVISION AND DRAFTSMAN
2002 - 2002
SUBMERSIBLE PUMP, WATER TREATMENT REPAIR, AND RESET ALIGNMENT
-
ESSO AT MAURITUIS AIRPORT
- RESPONSIBLE OF A TEAM OF SUPERVISION AND DRAFTSMAN
2001 - 2006
-
SOUTH AFRICA WITH DEGREMONT ON
- RESPONSIBLE OF A TEAM OF DRAFTSMAN
2000 - 2001
IN SOUTH AFRICA WITH DEGREMONT ON ST MARTIN PROJECT, SCREENING, GRIT DETRITOR, AERATION TANK, FINAL SETTLING TANK, BLOWER HOUSE THICKENER, DEWATERING BUILDING, VENTILATION DUCTING, SETTLEMENT TANK AND SO ON
-
MAINTENANCE
- CHIEF SUPERVISOR
1999 - maintenant
-
MECHANICAL SERVICES
- RESPONSIBLE OF A TEAM OF SUPERVISION AND DRAFTSMAN
1999 - 2000
OF THE CONSTRUCTION OF A NEW FACTORY (PRINCES TUNA
- AIR COMPRESSOR EQUIPMENT AND PIPE LINE ;
- POTABLE WATER TANK, PUMPING STATIONAND PIPE LINE ;
- FIRE HYDRANT WATER TANK, PUMPING STATION AND MAIN RING LINE.
- GENERAL ARRANGEMENT DRAWING OF BOILER ROOM AND STEAM PIPE LINE
- AS BUILT DRAWING
-
RESPONSIBLE OF A TEAM OF SUPERVISION AND PREVENTIVE MAINTENANCE
- BELT CONVEYOR
1999 - maintenant
MAINTENANCE AND PREVENTIVE MAINTENANCE AT CTBV ON PUMPS, VENTILATION, BEARING, BELT CONVEYOR, STEAM TURBINE, ALTERNATOR 32 MW AND CEKER MISS ALIMENT AND RESET ALIMENT, GEARBOXES, CHAIN CONVEYOR, COOLING TOWERS, ETC.
-
EDCC
- Directeur Maintenace
1999 - maintenant
-
SAVANNAH SUGAR FACTORY
- RESPONSIBLE OF A TEAM OF SUPERVISION AND
1998 - 1998
DRAWING OF A MODIFICATION CLARIFIER FOR SUGAR CANE JUICE.
-
SAVANNAH SUGAR FACTORY AS BUILT DRAWINGS
- DRAFTSMAN
1997 - 1998
AS BUILT DRAWINGS OF A WHOLE POWER GENERATION PLANT AT SAVANNAH SUGAR FACTORY.
-
OF EXPERIENCE IN SAVANNAH SUGAR FACTORY
- CHIEF MAINTENANCE OFFICER AND PREVENTIVE MAINTENANCE
1979 - 1999
TWENTY YEARS OF EXPERIENCE IN SAVANNAH SUGAR FACTORY, SEVEN YEARS WORKING AS
PROJECT WORKED ON