  • General Electric POWER CONVERSION - Site Manager - MARINE Commissioning

    2013 - maintenant Responsible of commissioning of Electric Propulsion Systems for LNG Carrier - South Korea
  • GE Power & Water - Commissioning Manager

    2012 - 2013 Responsible of the commissioning of the 3 Generators
    Central combine Cycle De Koudiet ED Draouch 3 x 400 MW
    Algeria
  • GE Power & Water - Site manager

    2011 - 2011 Responsible for installation and commissioning of a wind farm of 39 Wind turbines.
    The site was located at Petite Vallée - Quebec - CANADA
  • GE Power & Water - Site Manager

    2010 - 2011 Responsible for installation and commissioning of a wind farm of 18 Wind turbines.
    The site was located at Fere Champagne - France
  • GE Power & Water - COMMISSIONING MANAGER

    2008 - 2011 Last Assignments with General Electric :

    From June to November: Multiple interventions in France, Spain, Pakistan and training in Austria and Germany.

    June 2010: RANHILL - MALAYSIA: Responsible for the commissioning of a 75MW generator.

    May 2010: BEKASI - INDONESIA: Responsible for the commissioning of a 40MW generator and its auxiliaries.

    April 2010: MONGSTAD - NORWAY: Intervention to finalize the commissioning of two generators before the final acceptance of the installation by the customer.

    Dec. 2009 - March 2010: BELLAWAN - INDONESIA: Responsible for the commissioning of a gas turbine and the commissioning of a 120MW Generator and its auxiliaries.

    Sept. - Dec 2009: ISAB - SICILY: Commissioning of two 75MW generators and their auxiliaries.

    March – Sept 2009: MOHAMMEDIA - MOROCCO: Responsible for the commissioning of three generators of 120MW and their auxiliaries.

    Jan. - March 2009: ISAB - SICILY: Commissioning of two 75MW generators and their auxiliaries, training of new engineers.

    Sept - Jan 2009: ZAGREB - CROATIA: Commissioning of a generator of 75MW, with gas turbine.

    August 2008: CAM IS - TURKEY: Intervention for troubleshooting and restarting of a generator.

    April - July 2008: TEMA - GHANA: Commissioning of 120MW generator and its auxiliaries.

    March - April 2008: PERGEN - NETHERLANDS: Commissioning of two generators of 120MW and their auxiliaries.
  • ALSTOM / CONVERTEAM - SITE MANAGER / COMMISSIONING ENGINEER

    2001 - 2008 Last assignments:

    Nov. 2006 – Dec. 2007: MAASTEEL / CHINA: Responsible of the electrical erection and commissioning of two galvanizing lines.

    Sept. 2005 - Oct. 2006: TPCO / CHINA: Responsible of the electrical erection and commissioning of two Sendzimir and a skin pass mill.

    July 2005 - August 2005: SEVERGAL / RUSSIA: Commissioning support for the start-up of variable speed motors of two galvanizing lines.

    Dec. 2004 - June 2005: TAIYUAN IRON and STEEL / CHINA: Responsible of the commissioning of variable speed drive motors of the annealing line.

    Dec. 2003 – Dec. 2004: QINGDAO / CHINA: Commissioning of two Sendzimir and a skin pass mill.

    ( Previous missions spend in Finland, Indonesia, Iran .. )