Carthage Power Company
- PREVENTIVE MAINTENANCE COORDINATOR
Tunis2010 - maintenantOperation and maintenance of the 471MW combined cycle power plant.
- Installation engineer for all installed equipments, tasks includes:
o Protection relays maintenance for all electrical machines.
o Instruments installation and calibration.
o Predictive maintenance analysis.
o Monitoring system (GE) for all transformers.
o Maintenance and installation of cranes (Konecrane)
o Oscilloperturbographe ( BEN 5000 )
o Maintenance for circuit breakers MT/ BT
o Lock out /Tag out equipments ,
o preparation of operation procedures
o Major inspection of the 90KV and 225KV main transformers
o Oil treatment of the transformers
o Renovation of Protection relay of the main equipment
o Maintenance of the UPS system of the power plant