Menu

Simon MOUFTIEZ

En résumé

Mes compétences :
Technique
Ingénierie
Coordination
Relationnel
Welding
Procurement
Offshore Oil & Gas
HAZID
task force management
Technical coordination
System Testing
QA/QC supervision
Pro/ENGINEER
Onshore Oil & Gas
Offshore experience
Microsoft Word
Microsoft Project
Microsoft PowerPoint
Microsoft Excel
FMECA
Contract option award preparation and negotiation
Consolidations
CATIA

Entreprises

  • Consultant pour TOTAL E&P Angola - Responsable Technique / Ingénieur principal package Subsea

    2012 - maintenant Responsable technique du package Subsea pour un projet d'optimisation de production sur un FPSO existant (Girasol) consistant au développement, fabrication et installation de 2 stations de pompage sous marines (1500m) intégrant chacune 2 pompes multiphasiques high boost.
  • TOTAL E&P Angola - Subsea Multiphase Pump Package Leader & STAT Marine LTD Consultant

    2012 - maintenant Package consisting of 2off 300t Manifold module + 6 off high boost pumping unit (60t, 130bar, 0 to 100% GVF, 2.3MW)+ 2off
    support & levelling structure, 2off suction pile + subsea tooling & ancillaries.
    * Detailed Engineering (@One Subsea, Bergen- Norway):
    - Technical assessment of Contractor engineering (design review, specification, drawings, data sheet, assembly
    procedures, test procedures, interface system and ROV access study)
    - Coordination with head office technical department ;
    - Procurement folow up and expediting towards sub vendors (forging, valves, tools...).
    * Construction and testing (@One Subsea, Radoy/Horsoy- Norway):
    - Fabrication documentation review (Inspection and test plan, welding procedures, NDE, coating...) ;
    - Assembly follow up and expediting (fabrication and testing sequence analysis recovery plan when required)
    - System testing preparatory work and execution ;
    - Company Site representative with QA/QC supervision and high focus on HSE
    - Management of non-conformity and technical deviation.
    * Installation:
    - Engineering work with TOTAL affiliate in Angola for field intervention and Pump Unit installation/recovery scenario
    - Review of sea fastening, rigging arrangement and instalation procedures
    - Technical coordination between installation contractor and SPS contactor.
    - Company representative onshore/offshore for instalation campaign of subsea station
    * Commissioning/start up:
    - Assistance of subsea commissioning ;
    - Coordination of vendors mobilization and follow up ;
    - Responsible of task force management for offshore commissioning/start up trouble shooting
    * Contract:
    - Designated Manager for the completion and close out of the contract since November 2015
  • TOTAL E&P Angola - Flowbase and Tie in Package Technical leader

    2011 - 2012  Detailed Engineering (@FMC, Kongsberg- Norway):
    - Technical review of SPS Contractor engineering documentation ;
    - Engineering and procurement follow up ;
    - Contract change order review.
     Construction (@FMC subcontractors, Norway and Angola):
    - Fabrication documentation review (Inspection and test plan, welding procedures, NDE, coating...) ;
    - Fabrication progress follow up ;
    - Expediting for Flowbase and Tie in main equipment at FMC subcontractors (6 off) ;
    - Coordination manager and technical support for Angolan project team on fabrication site.
     Installation (Offshore Angola Block 17):
    - Preparation of installation phase for SPS equipment (coordination of tooling refurbishment, review of Installation
    Contractor procedures and participation to HAZID) ;
    - TOTAL SPS representative Onshore/Offshore during GirRI project manifold system installation campaign (March
    2012).
  • TOTAL E&P Angola - Subsea Production System Interface Leader & Consultant

    2009 - 2011 * Detailed Engineering phase (FMC Kongsberg, Norway):
    - Technical coordination between GirRI project other packages and SPS package ;
    - Management of SPS Contractor Interfaces queries ;
    - Design review, FMECA and RAM analysis participation ;
    - Contract option award preparation and negotiation with SPS Contractor
    - Follow up and expediting on production jumper fabrication for GirRI project first oil.
    * Basic Engineering phase (Doris Engineering Paris, France):
    - Battery limit definition for SPS Contractor scope of work ;
    - Tender phase participation with SPS tenderer ;
    - SPS team representative at Basic Engineering contractor offices (HAZID, SPOT, PTR, BE documentation review
    and close out).
  • Consultant pour TOTAL E&P ANGOLA - Subsea production system Interface Leader

    2009 - 2011 Responsable, pour l'équipe en charge des équipements de production sous marin, de la mise en place et du suivi du management des Interfaces techniques entre les différents contracteurs pour un projet d'exploitation pétrolière en deep offshore.
    -> Coordination technique
    -> Définition et gestion des responsabilités en marge des différents contrats
    -> Représentant du package subsea pour la phase de basic engineering
  • PSA PEUGEOT CITROËN - Coatings Engineer & Consultant

    2007 - 2009 Project leader for reduction of diversity and coatings industrialisation lead time optimisation;
    - Scheduling and follow up evolution of process of paint shops;
    - Projects support for industrialisation of new O.E.M. coatings.
  • Consultant pour PSA Peugeot Citroën - Leader Technique Peinture

    2007 - 2009 Responsable lancement matière finition pour le métier Peinture - PEUGEOT CITROËN PSA (78 Poissy)
    - Garantir les lancements matières dans le respect des procédures PSA (coûts, délais, qualité)
    - Gérer la diversité peinture et la politique Technique-Achat matière finition
    - Optimiser et améliorer les procédures de lancements matières
    - Assister et accompagner les unités peinture du groupe PSA
    - Suivre les fournisseurs matières (coûts, parts de marché, qualité prestation et produits…)
  • Groupe PSA - Painting project leader

    Rueil Malmaison 2005 - 2007 Car body manufacturing consolidation;
    - Management of the Car Automated Handling system improvement project;
    - Definition of the sealer and painting maps (cost and quality);
    - Responsible for paintshop project deliverables (productivity, quality and cost management).
  • Consultant pour PSA Peugeot Citroën - Chargé de projet Peinture

    2005 - 2007 Chargé de projet Peinture pour l’industrialisation de la 207SW - PEUGEOT CITROËN PSA (78 Poissy)
    - Participer au développement et à la mise au point de la caisse
    - Définir l’étanchéité et le revêtement peinture
    - Garantir la tenue des livrables pour l’industrialisation du véhicule
    - Gestion des risques, des ressources et des investissements
    - Pilote Ingénierie Métier (reporting, création et déploiement d’indicateurs pour le référentiel tableau de bord du métier peinture, création du planning référentiel d’un nouveau schéma de développement véhicule)
  • VALEO Switches & Detection Systems - Projet de fin d'étude: Ergonomie produit

    Paris 2003 - 2004 PFE de 7 mois: Etudes ergonomiques, développement technique et prototypage de commandes pour tableau de bord automobile.

Formations

Annuaire des membres :