Younes BENNANI

COURBEVOIE

En résumé

Over 8 years experience in project control including over 7 years in Oil & Gas industry on behalf operator and contractor companies. Involved on all project development phases from initiation till start-up. Looking for new opportunities.

Mes compétences :
Planning ingénierie
Gestion de projet
Avancement et controle de projet
Planning stratégique
Planification
Reporting
PrimaveraP6
Coordination
MS project
Gestion
Qualité
Management
PMI

Entreprises

  • Total - Project Planning, Progress & Reporting Engineer

    COURBEVOIE 2013 - 2017 Moho Nord Project for Total E&P Congo
    o PCF ‘Planning Chemin de Fer’ team leader ( PCF: linear scheduling method used on MOHO Nord project in order to prevent clashes between the different vessels during the offshore installation operations and a better follow-up of offshore operations.)
     Responsible for planning coordination of all offshore activities in Congo.
     In charge of PCF overall optimisation in order to guarantee an early Moho Nord First Oil.
     In charge of commissioning and start up sequence update.
     Check the possibility of SIMOPS and COMOPS operation.
     Analyse during the preparation phase all shutdowns in order to reduce their global duration.
     Assure the update of the operations planning (5 weeks) (use of the linear scheduling method) on a weekly basis.
     Register day by day and represent on a map the daily progress in term of equipment installation (subsea).
    o Planning leader for the packages: Drilling, Geosciences/ Subsurface, Alima, Djeno and Nkossa fields.
    o Assist and, when necessary, subrogate the Project Planning Leader in organising and conducting planning and scheduling activities.
     Overall Integrated schedule ‘OIS’ database update, issuance of OIS level 0 up to level 2 schedules, critical paths, forecasting dates, etc.
     Preparation of additional schedules and simulations as and when required by Project Management.
     Update TEPC ‘Total Exploration & Production Congo’ affiliate schedules in the TEPC data base and weekly issuance of 5 Weeks (35 days) Look Ahead for Alima, Djeno and Nkossa fields.
     Monthly update and issuance of Moho Nord project 3 Months look ahead schedule in TEPC database.
     Assistance of building 24 months TEPC schedule on a quarterly basis.
     Monthly Update and issuance of schedule Interfaces.
    o Organize and lead the progress and reporting functions of the Project.
     Issue project reports (highlights, weekly, monthly and six months) to the corporate PJC ‘Project & Construction’ department and / or other predefined internal and external recipients.
     Ensuring that all reports are issued in compliance with the corporate requirements.
     Preparation of additional reports or presentations as and when required by project management.
     Participating to or conducting internal quality audits in relation with QA Manager in view of controlling the respect of progress and reporting internal procedures.
     Preparation, update and monitoring the progress reporting tool and project key indicators.
     Control and monitoring of progress tables and S-curves of project packages and issuance of project overall progress table and S-curves.
     Progress reporting to the partners and the corporate PJC department.
    o Checking and commenting Packages, contractors or vendors procedures, schedules, cost, invoices and progress.
    o Assistance of update PDC ‘project development cycle’, LOP’ life of project’ curve and CAPEX.
    o Complying with HSE requirements and taking part in the implementation of the Safety Culture process “IMPACTS” within Moho Nord Project.
    Moho Nord Subsea Exploration and Production Project
    The $10bn project, located 75Km off the coast of Pointe Noire in the Republic of Congo.
    The project split in 15 packages: Drilling, TLP, FPU, SPS, UFR, ALIMA (existing FPU), Djeno onshore field and Nkossa existing platform; and transversal packages such us field operations, HSE, quality, local content, etc.
    28 subsea wellheads tied back to floating production units (FPUs) and with 17 more wells from a new tension leg platform (TLP). The construction involves more than 50 subsea structures, 230km of rigid pipelines, 23km of flexible pipes, 50km of umbilicals and numerous manifolds, pumps, control system components and multiphase jumpers. By 2016, 140,000 (boe/d). TOTAL as operator 53.5%, CHEVRON 31.5% & and state-owned Congo national petroleum company (15%).
  • Technip - Planning, Scheduling and Project Control Engineer

    Paris 2009 - 2013 - Prepare Project breakdown structures (WBS, PBS, CBS, OBS, etc.), Project Planning Procedure, Physical Progress Measurement Methodology & Project Co-ordination Procedure.
    - Develop the 90days & levels 1,2,3 “Baseline” schedules by co-coordinating with all departments
    - Merge schedule activities: Engineering, Procurement, Construction, Commissioning & Interfaces
    - Update and monitoring project schedule (broken line, critical path, forecasting date, etc.)
    - Earned value management : implementation , control and monitoring
    - Proposal of mitigation actions plan, estimation of the residuals and allocation of contingencies
    - Daily monitoring and reporting of weekly/monthly progress report with variances as per baseline schedule, progress s-curve and manpower histogram and productivity.
    - Control, monitoring and monthly reporting of forecast expenditures against approved budgets, schedule impacts and material cost variance
    - Conception of project performance indicators and follow-up.
    - Identification, quantification of the risks and opportunities (probabilities, cost and schedule impacts)
    - Participation to the building of the project claim for compensation dossier

    Main Projects :

    ****MARTIN LINGE Project ¤ EPSCC contract : Hild Oil & Gas field: PLATFORM Offshore Norway “North Sea” . Topsides composed of utility, process and flare modules, as well as a living quarter with 95 single-bed cabins. water depth 114m

    ****HEJRE Project ¤ FEED & EPC contract :PLATFORM Offshore Denmark “North Sea”
    Topsides , Jacket , water depth 70m

    ****GirRI development Project :FPSO2 Topside modification: Implementation of subsea multiphase pumps (MPP) to improve production activation

    ****BADRA Oilfield Project ¤FEED & EPC proposals .

    ****BASRAH Ultra Low Sulfur Diesel project ¤EPC proposal
  • Senseor - Junior Project Manager

    2008 - 2009 ****Development project management tool :
    Deployed a tool of project management to improve procedures for planning and monitoring of projects by the various project managers and better managing costs, time and resources associated with projects.

    ****Implantable wireless SAW sensor for monitoring blood pressure:
    My mission was to provide a support to my manager regarding design and developement of products.I was in charge also to define scope, planning and ensure availability of project's deliverables, to respect the costs and limits according to technical specifications

    ****Design antennas :
    The purpose is to develop various antennas for each industrial application through customer requirements and needs
  • Infineon - Analog design and mixed engineer

    LA CHAPELLE SUR ERDRE 2008 - 2008 ****Electrical Modelling of Data Retention Faults in embedded-SRAM :
    Development of a new memory plan with no retention fault.I contributed to define scope and planning, attend and perform simulations and test the functionality of the full circuit