RINA Services
- Project Expeditor : Project: NAWARA GAS TREATMENT PLANT (NAWGTP), Gabes Tunisie
2015 - 2016
Follow up Workshop Prefabrication Pressure Vessels:
Responsible of purchase order management (Expediting, Inspection and shipping activities coordination)
Purchase Orders issue/monitoring/expediting follow-up (desk expediting)
Fabrication Schedule analysis
Sub-Orders issue follow-up for delivery dates consistency check
Check compliance of Suppliers activities with contractual deliveries
Kick Off Meetings and Pre-inspection meetings coordination and management
Expediting/Inspection Agencies supervision and coordination for Inspectors/Expeditors Recruitment
Support, coordination and monitoring of Inspection activities
Support to Suppliers during Shipment preparation (required documents for export);
Support to Quality department for preparing/implementing internal procedures
Follow up of the drawings approved for Construction
Management of the NCRs
Verification of the application of the standards; specifications, ITP and quality procedures of all the clients
-
Ansaldo Energia
- QA/QC Engineer
2014 - maintenant
QA/QC Engineer : within Ansaldo Energia as part of the project to build the combined cycle power plant 420 MW of Sousse Tunisia: 01/04/2014 until now.
- Project: Construction of combined cycle power plant 424 MW Sousse “D”
- OWNER: STEG (Tunisian Company of Electricity and Gas)
- CONTRACTOR : Group Ansaldo Energia/ SNC Lavalin
- SUBCONTRACTOR : General construction/ CERI, Paratino/MIG, Socomenin, SCIN, ETELEC, Africisol…
- STANDARDS: EN 287-1;EN ISO 15614-1; EN ISO 15609-1; ASME I-V;ASME IX; API 650;B31.1; B31.3;API 650
- THIRD PART: TIC, PI, Seybold, BCAT, BCA
Development of Preliminary QA/QC documentation (Method statements, Quality Plan,
Work procedures…).
Reception material Inspection and conformity with specifications and certificates.
Follow up and supervision of piping spool’s fabrication (shop welds) & erection (field welds)(BOP; Turbo-group & Boiler piping).
Coordination of piping supports fabrication and erection.
Elaboration and follow up of ITPs (Inspection and Testing Plan) according the requirements
Preparation of the preliminary WPS (carbon steel, stainless steel, alloyed steel P11, P22 & P91, Duplex).
Approval of preliminary WPS (Welding Procedure Specification) and PQR (Procedure of Qualification Record) by the third part.
Welding Qualification Test (WPQ + NDT request) with the third part.
Reporting to the Quality, Construction and project managers.
Participation to the weekly meeting with the final client
Monitoring and follow up of the Welding book (65000 inch welded).
Resolving all the modifications on the site.
Control and follow up of the subcontractor’s activities.
Management & follow up of the NCRs.
Supervision and control of the erection activities of Turbo-group (Diffuser Gas Turbine; Generator; Steam Turbine; Air intake system & Condenser).
Steel structures inspections: welding, Dimensional, verticality, bolts tightening, sandblasting and painting….
Dimensional; Welding; Sandblasting; hydro-test and painting controls of the 5 Tanks
Dimensional; welding, Sandblasting and painting control of the condenser
Welding Inspection of the casing and outlet duct of the boiler.
Control of erection and welding activities of the different parts of the boiler (RH; SH; Economizer; collectors, casing).
Supervision and control of the erection activities of the BOP (Balance Of the Plant): Auxiliary boiler, station seawater pumping, gas treatment stations, desalination and demineralization station, Fuel pumping station…
Coordination of NDT controls (programs, reports & follow up).
Hydrostatic Test: prescription of Test Pack.
Control of the subcontractor’s documentation.
Coordination with the subcontractors and the final client.
Review of Final documentation.
-
SNC Lavalin
- QA/QC Engineer
Ivry-sur-Seine
2012 - 2014
: within the group SNC Lavalin / Ansaldo Energia as part of the project to build the combined cycle power plant 420 MW of Sousse Tunisia: 01/05/2012 to 31/03/2014.
- Project: Construction of combined cycle power plant 420MW Sousse “C”
- OWNER: STEG (Tunisian Company of Electricity and Gas)
- CONTRACTOR : Group SNC Lavalin /Ansaldo Energia
- SUBCONTRACTOR : MIG, PIRECO, ETELEC, MARS, Africisol…
- STANDARDS: ASME I-V;ASME IX; B31.1; B31.3;API 650
- THIRD PART: TIC, PI, Seybold, BCAT, BCA
MISSION:
Elaboration and follow up of ITPs (Inspection and Testing Plan) according the requirements
Preparation of the preliminary WPS (carbon steel, stainless steel, Duplex).
Approval of preliminary WPS (Welding Procedure Specification) and PQR (Procedure of Qualification Record) by the third part.
Welding Qualification Test (WPQ + NDT request) with the third part.
The drafting of plans, inspections related to mechanical activities
Treatment, together with the quality control coordinator, non- compliances and associated corrective actions related to mechanical work
Participation in pressure tests and validation of manufacturing records
Participation in meetings of establishing order with the customer and outsourcing.
Conformity of piping fittings & consumables with specifications and certificates.
Check of material arrival.
Preparation, followed and receiving mechanical work : - Power Train: Gas turbine, Steam turbine, Generator, Condenser & Auxiliary Equipment turbine and generator (fuel injection systems, air filter, compressor...) - Balance of Plant B.O.P (auxiliary items):
Follow up and supervision the installation of the recovery boiler (HRSG) work: panels, structure, balloons, insulation, painting, dimensional inspection, welding (visual inspection, PT, ultrasonic and RT...)
Followed assembly work station seawater pumping: recirculation pumps, auxiliary pumps, cofferdams, on filters, BONA pipes, tanks and skids electro-chlorination...
Followed assembly work station conditioning natural gas: gas filtration skids, ball drains, hot water boiler, piping, supports...
Followed work equipment installation of desalination and demineralization: Osmoses, Multimedia filters, CIP tank, pumps supplies, CIP pump, filter cartridge...
Followed installation work of aid the recovery boiler: Auxiliary boiler, boiler feed pumps, pumps and exchangers blackish, recirculation pumps boiler exchangers, boiler blow down, boiler sampling, chemical injection thermal cycle, generator...
Follow up and supervision of piping spool’s and supports fabrication (shop welds) & erection (field welds).
Management & follow up of the NCRs.
Dimensional; bolting; tightening & verticality controls of the steel structure.
Welding, Handblasting and painting Inspection of the steel structure.
Supervision of erection and follow up of welding activity of the tanks.
Dimensional; Welding; handblasting; hysrotest and painting controls of the Tanks.
Coordination with the third part for NDT Controls.
Control of the subcontractor’s documentation.
Coordination with the subcontractors and the final client.
Review of Final documentation.
-
Thyssenkrupp elevator tunisien branch
- QA/QC Engineer
2010 - 2012
within the company ThyssenKrupp as part of the project to build International airport Enfidha Hammamet Sousse Tunisia for TAV Airport from 01/10/2010 to 20/04/2012.
MISSION:
Monitoring and receiving mechanical works: - Installation of steel structure (conformity, verticality, alignment, tightening, dimensional control, welding...) - Installation of Baggage Handling systems (BHS) ‘Vanderlande’: conveyors, motors, X-Ray, belts fixations, rollers- Installation of Sorter System ‘Beumer’: conveyors, linear motors, bar code reader... - Installation of hydraulic and electrical elevators ThyssenKrupp Elevator. - Installation of Escalators and travelators ThyssenKrupp. - Installation of Passengers Boarding Bridges (PBB) & 400Hz.
Treatment, together with the quality control coordinator, non- compliances and associated corrective actions related to mechanical work.
Participation in meetings of establishing order with the customer and outsourcing.