Bouygues Travaux Publics
- Construction Deputy Manager
GUYANCOURT2013 - maintenant
Bouygues Travaux Publics
- Construction Project Engineer
GUYANCOURT2012 - 2013Chernobyl New Safe Confinement - NOVARKA:
- Arch Construction coordinator: coordination of the Primary (18 000 tons), Secondary (4 000 tons) & Temporary (5 000 tons) Steel structures Erection sections.
- Responsible of Secondary Steel Structure Erection (4000 tons)
- Responsible for Jacking & Skidding of the Arch Steel Structure: 6 Jacking operations from 6 000 tons till 12 000 tons and 3 skidding operations from 12 000 tons on 100m till 30 000 tons on 250m.
Bouygues TP
- Construction Engineer
Paris2010 - 2012Chernobyl New Sfae Confinement - NOVARKA:
Preparation of Arch Steel structure Erection - Preparation and follow-up of call for tender for the supporting works of the Arch Structure erection:
- Design and Supply of Scaffolding (1M EUR)
- Post-Tensioning works for Temporary structure anchorage (1M EUR)
- Manufacturing and Supply of 4 000 tons of Secondary Structures (8M EUR)
- Purchasing of equipment and tools for Arch Construction (8M EUR)
Preparation of Arch Steel structure Erection - Construction methods: creation of construction documentation (Process Charts & Lift Plan)