Saipem
- Offshore Project / Field Engineer
Montigny-le-Bretonneux
2014 - maintenant
Since July 2016 – Project Engineer for BP Miller decommissioning – North Sea
On the platform:
- Follow up of preparation decommissioning works
- Preparation works coordination
- Client interface for technical parts of the preparation works
In London office:
- Pre-Engineering for the platform-based preparation works before platform removal by S7000
- Work Pack Overviews and Job Cards development
- Scope of Work preparation for Subcontractor (scaffolding / rope access technician / NDE / UAV services)
- Survey on the BP Miller platform
October 2015 / June 2016 – Ersai 1 (Pipelay Barge) for Kashagan 2 project (32” CLAD pipeline) – Kazakhstan
- Operations preparation (task plans, technical queries, rigging)
- Operations coordination/follow-up with shift supervisor
- Provide technical support to vessel superintendent and project team
- Follow up of winter maintenance
- Preparation of dry dock (vessel support installation)
- Vessel reporting
July 2015 / September 2015 – S355 (Derrick Lay Barge) for ENI Bonaccia NW project (10”+6” piggyback pipeline) – Italy
- Operations preparation -> Initiation / Laydown / Stinger connection and disconnection
- Operations coordination/follow-up with shift supervisor
- Provide technical support to vessel superintendent and project team
- Material follow up during mobilization/demobilization phases
- Lay up of S355 -> Manitowoc crane offloading (task plan, lift plan, jetty preparation)
- Vessel reporting
July 2014 / May 2015 - PLBH (Pipelay Barge) upgrade for BP Shah Deniz 2 project – Baku (Azerbaijan)
- Follow up and application of upgrade procedures and drawings
- Heavy equipment installation -> Task plan, lift plan and lifting preparation
- Provide support to upgrade team and all vessel department
- Interface role with onboard subcontractors
- Vessel reporting
-
CGG
- Operations & Performance Analyst
Paris
2013 - 2014
Method & Performance of the Land Acquisition Division
• Intervention on the field to improve performance reporting tools (“Shallow Water / Land” in Abu Dhabi and “OBC” in Kuwait)
• Project Manager on operational performance projects. Responsible for the organization, planning, project charter, communication between departments (interactive map and Prospectors competencies on the field)
-
CGG
- Operations & Performance Analyst
Paris
2013 - 2013
Method & Performance of the Land Acquisition Division
• Project of operations progress on an interactive map integrating production monitoring (surveying, drilling, ...) and key indicators for managers and customers
-
Sia Partners
- Graduation project - CentraleSupélec
Paris
2012 - 2013
Storage integration for managing intermittent production from renewables (Wind & Solar)
• Literature review on existing electricity storage technologies
• Techno-economic model of these storage technologies performance
-
GDF SUEZ
- Gap year - Strategy Analyst
COURBEVOIE
2011 - 2012
Strategy & Prospective of the Global Gas & LNG Business Line in charge of Exploration & Production (E&P) and LNG supply
• Realization of notes for the top management on Oil & Gas and Utilities players (30 companies studied including E.ON, Centrica, Shell, Eni, BG, CNOOC,...) including the key indicators on finance, strategy (SWOT analysis) and operation (E&P, gas supply, LNG, transportation, distribution, sales, power generation)
• Participation in strategic regional studies (economic, energy policy, gas value chain and regulation): Middle East / North Africa and Sub-Saharan Africa -> 30 countries studied
• Participation in ad-hoc studies on the competitors strategy (unconventional gas, LNG,…)
-
Château Luchey-Halde
- Worker internship
2010 - 2010
Worked in the vineyard (thinning) and winery (inventory, order picking)