Patrick Md Ali LE FLOCH

LANESTER

En résumé

Project manager / Construction manager/PMC
International experience in FRANCE,SULTANA OF OMAN, SAUDI ARABIA, BANGLADESH, CAMEROON, MALAYSIA of Oil and gas industries, civil work, Electro-Mechanical erection, instrumentation, naval construction, supervision, management and maintenance in heavy / medium industry.

Mes compétences :
Project Management
Construction Manager
PMC
Pétrole
Management
Ingéniérie
Gestion de projet
Energie
Autocad
instrumentation
supervision
Maintenance
Microsoft Project
Microsoft PowerPoint
Microsoft Excel
Siemens Hardware
installation
general management
Quality Control
Procurement
Assembly Plants
instrumentation supervision
fabrication supervision
Steam Turbines
Quality Assurance
Project planning
Plumbing
HSE plan development and implementation
HSE general management
Generators
Contract management
Civil work supervision
Civil Engineering
value engineering
project facilities construction supervision
process maintenance
process development
pipeline supervision
leisure boat design
industrial unit development
generator management
fabrication training
equipment procurement management
develop HSE plans
detail preparation
cost estimation
contract negotiation
commissioning management
Win Pcs implementation
Weather station development
Transformers
Tasks Management
Suppliers Bid selection
Steel
Software development
Si

Entreprises

  • Euro Petroleum Consultants - Vice President

    2015 - maintenant Project Business development in Asia
    Function Vice President
    Tasks
    * Promote the image of EPC and the Consulting Activities in the regions, according to the guidelines and instructions of EPC relating to EPC Consulting Activities.

    * Identify all projects, at their earliest stage in the regions, which could involve Consulting Activities and shall convey to EPC all available information relating to such projects.

    * Follow up on Proposals in the most appropriate manner with a view to successful results.

    * Make all necessary arrangements and provide all reasonable assistance to EPC for all administrative steps in connection with Proposal in the region, such as, but not limited to, taxation matters, obtaining visas, customs and tax clearances, reservations of accommodation, arrangements for business appointments, that EPC may think suitable at any stage of the Proposal.

    * Provide all reasonable assistance Follow up on the processing of EPC' relevant invoices with EPC Clients relevant departments.

    * Prepare a detailed monthly report and timesheet on all ongoing consulting activities. ;
  • Euro Petroleum Consultants - PMC Coordinator

    2014 - maintenant SONARA extension project
  • Euro Petroleum Consultants Ltd - Construction manager

    2011 - 2014 Refinery extension project
    vacuum distillation.
    Revamping.
    Storage.
  • Euro Petroleum Consultants - Manager & project coordinator

    2011 - 2015 Company Euro Petroleum Consultants Lieu : Cameroon
    Project SONARA Refinery extension project phase 1
    Function PMC Construction manager/ project coordinator
    Tasks * ~ 300M EUR project - ~1200 project staff
    * Construction ;
    * Managing the Project management teams with multi-discipline refinery staff and PMC experts ;
    * Lead the construction supervision team
    * Contract management
    * Cost control management. ;
    * Verification and validation of machinery and construction contract commercial and technical Bid evaluation
    * Verification and validation of project invoices for SONARA.(client)
    * Interface between SONARA and general project co-contractor
    * Administration ;
    * Preparation of monthly project progress report. ;
    * Leading the weekly and monthly progress meeting. ;
    * Leading the Quality and HSE meeting.

    Results Project management team organization.
    Client project cost control organization
    Construction design challenge for value engineering

    Tools MS power point, MS Project, Primavera, excel
  • Aquality - Engineering manager

    2010 - 2010 Project Water treatment plan
    Function Engineering manager for the Bid phase
    Tasks * Engineering consultant contract management ;
    * Engineering cost estimation and negotiations ;
    * Drafting of the Contract of Engineering consultant (WP) ;
    * Bid planning and Project planning
    * Deliverables ;
    * Definition and finalization of the deliverable list for the Bid and execution phase

    * Engineering teams ;
    * Preparation of the engineering team resource requirement including job profile for each position.

    Results 6M AU$ save in the contract negotiation due to tied and detail preparation of deliverable list.

    Tools MS power point, MS Project, Primavera, excel
  • Degremont - Engineering manager

    Paris La Défense 2010 - 2010 Engineering consultant contract management
    o Engineering cost estimation and negotiations
    o Drafting of the Contract of Engineering consultant (WP)
    o Bid planning and Project planning
    Deliverables
    o Definition and finalization of the deliverable list for the Bid and execution phase

    Engineering teams
    o Preparation of the engineering team resource requirement including job profile for each position.
  • EPC Consult - Director

    2009 - 2010 Project Consulting
    Function Director
    Tasks * High raise steel building project profile ;
    * Selection of design and construction firms ;
    * Introduction of dry wall system in civil construction market.
    * Developing tourism project. (Asian Trek Discovery Ltd)

    Results 25 storied steel building project profile completed
    ATD in operation

    Tools MS power point, MS Project, excel AUTOCAD
  • EPC Consult - Directeur

    2009 - 2010 High raise steel building project profile
    Selection of design and construction firms
    Introduction of dry wall system in civil construction market.
    Developing tourism project. (Asian Trek Discovery Ltd)
  • SNF Floerger - Project Manager

    2006 - 2009 Project Marmul Polymer Flooding Project- PDO (SHELL)
    Function Project Manager
    Tasks From the Detail Design, procurement, construction to Pre-commisioning stage I was in charge of the project management in Oman. The project of 160M$ included:
    Water treatment plan of 80 000m3/d (IGF and HDBF system)
    Polymer injection plan with polymer silos, polymer slicing unit, maturation tanks and 30 injection pumps.
    75 km of flow lines connected to 27 injection wells.
    * FEED in France
    * Main Contract drafting and project planning ;
    * Engineering consultant contract drafting and negotiation. ;
    * Construction contract drafting and negotiation. ;
    * Lead the Piping and civil engineering package ;
    * HSE plan and QA plan
    * Engineering Phase at Muscat
    * Leading the French engineering teams
    * Mechanical engineering
    * Process engineering
    * Civil engineering
    * Electrical/instrumentation engineering ;
    * Piping engineering
    * HSE management
    * Quality management
    * Project control teams
    * First SNF representative to PDO
    * Procurement
    * Leading the Procurement management team
    * Suppliers Bid selection
    * Inspections and FAT
    * Construction
    * HSE general management
    * QA/QC general management ;
    * 650 to 1000 work force mobilized at site during 22 months ;
    * Camps and project facilities construction supervision ;
    * Civil work contractors' management. (8000 m3 of concrete) ;
    * Civil work supervision ;
    * Equipment erection /fabrication supervision. ;
    * Piping and pipeline supervision (75km of pipeline) ;
    * Electricity and instrumentation supervision ;
    * Pre-commissioning
    * Win Pcs implementation
    * Pre-commissioning general management

    Results Project delivered and in operation
    Tools MS power point, Primavera, MS Project, excel AUTOCAD
  • SNF Floerger - Project Manager

    2006 - 2009 Project manager of Marmul Polymer Flooding Project.
    From the Detail Design, procurement, construction to Pre-commisioning stage I was in charge of the project management in Oman. The project of 160M$ included:
    Water treatment plan of 80 000m3/d (IGF and HDBF system)
    Polymer injection plan with polymer silos, polymer slicing unit, maturation tanks and 30 injection pumps.
    75 km of flow lines connected to 27 injection wells.
  • SAUDI OGER - Directeur des corps technique secondaire

    Riyadh 2005 - 2006 Responsible for 4 departments (HVAC, HCU,LCU, Plumber) for the all construction project of the royal family. Administrative, technical and financial management. 1000 employees. Organization of the follow-ups, optimization of the coordination of the departments, definition of intervention procedures and follow-ups of the tasks. Hygiene and safety at work.
  • SAUDI OGER - HEAD SERVICE MANAGER

    Riyadh 2004 - 2006 Project ELECTRICAL, PLUMBING, HVAC, LOW CURENT DEPARTEMENT
    Function HEAD SERVICE MANAGER
    Tasks * Responsible for 4 departments (HVAC, High current, Low current, Plumbing) for the all construction project. (1600 staff)
    * Reporting to the top management. ;
    * Organization of the follow-ups, optimization of the coordination of the departments ;
    * HSE plan development and implementation ;
    * Introduction to the ISO 9001


    Results * Optimization and centralization of the material management
    * HSE plan development and implementation

    Tools MS power point, MS Project, excel
  • Fisher Ship Yard - Project manager

    2002 - 2004 Project Yacht and ship building project
    Function Project manager
    Tasks New activity of Ship construction start up in the Ship yard
    * Construction yard development ;
    * Lofting and fabrication training.
    * Carpentry yard and training ;
    * Planning and project profile ;
    * Leading the deep sea fishing trawler engineering team


    Results * 45 ft patrol boat for Bangladesh navy
    * 42 ft passenger boat ;
    * Completion of pilot project of leisure boat design, construction and exportation to Europe

    Tools MS power point, MS Project, excel , AUTOCAD
  • Fraciab - Director Instrumentation

    2001 - 2002 Project Sajahal paper mills power plan
    Function Director Instrumentation and control
    Tasks * I am in charge of the engineering procurement and installation for Instrumentation, tripping controls for Boiler, turbine and generator management system.
    * Second hand, steam power plant with 85T-gas boiler. ;
    * SOGET steam turbine 4MW
    * ALSTOM generator 5.5KV.


    Results * Plan in operation
    Tools MS power point, MS Project, excel , AUTOCAD
  • TRIMOD - Executive Director

    2000 - 2001 Project Sweater and Buying house management
    Function Executive Director
    Tasks During the absence of the Managing director, I am in charge for one year of the management of:
    * A sweaters factory with 600 employees. ;
    * Managing the Buying house and handling the sample campaign of the 2002 winter season.


    Results * Succeed the 2002 winter season and hand over back the management to the MD
    Tools MS power point, MS Project, excel
  • ZAMIL STEEL - Construction Director

    1999 - 2000 Project Pre-engineered steel building erection
    Function Construction Director
    Tasks * Management and supervision for the construction of pre-engineering building.
    * Mobilization of local contractors ;
    * Construction sites follow-up ;
    * Technical adviser for local erection companies.


    Results * 15 building erected in 6 months in garments sector in Bangladesh
    Tools MS power point, MS Project, excel
  • AREL Ingenierie - Construction Director

    1994 - 1999 Project Jute Line Improvement Project at Sylhet Pulp and Paper Mills
    Function Construction Director
    Tasks Management in Bangladesh of the Jute Line improvement Project at Sylhet Pulp and Paper mills (8M$).
    * Selection and contracting to local civil construction companies the piling and building construction package.
    * Selection and contracting to local Mechanical, piping, electrical construction companies the plant construction packages
    * Construction supervision
    * HSE general management
    * QA/QC general management ;
    * 120 to 300 work force mobilized at site during 17 months
    * Civil work contractors' management. (1000 m3 of concrete)
    * Civil work supervision ;
    * Equipment erection /fabrication supervision. ;
    * Piping supervision ;
    * Electricity and instrumentation supervision

    * , pre-commissioning and commissioning management


    Results * Erection completion certificate
    * Project completion certificate ;
    * Company claim submission to client for 1M$ (0.5M$ succeed)

    Tools MS power point, MS Project, excel
  • PROVAL - Maintenance Manager

    1991 - 1994 Description: Frozen food factory PICARD products and others

Formations

Réseau