COURBEVOIE
Actuellement, je suis en poste en Indonésie en tant Superintendent E/I (pour le compte de TOTAL) pour le projet KAOMBO.
David BRETON
Le Boissard
73520 Saint Béron, France
Tel. +33 (0)6.19.86.11.30
DOB: 25/06/1974, married, 2 Children
d.breton@hotmail.fr
Electrical / Instrumentation
Supervisor & Coordinator
Offshore E/I manager
PROFESSIONAL EXPERIENCE
To year 01/2014 from 09/2014. Instrument Construction Supervisor TOTAL CLOV FPSO (D2M-group).
Task performed: Supervision of Construction activities. Hook-up following and pre- commissioning. Daily meeting for Progress & Organization task. Reporting and weekly punch list follow-up.
Year 2012 Mechanical Completion. Construction Completion Coordinator on KASHAGAN DEVELOPMENT EXPERIMENTAL PROGRAM.in KAZAHKSATAN for ROSETTI MORENO IT.Ensure the daily programming of all site works is performed in accordance with the Company construction program.
Year 2011 E/I Construction supervisor on FPSO KIZUMBA B, EXXON MOBIL ANGOLA
SPIE ANGOLA
Revamping, hook-up & Integration SATELITE project (phase 1
Supervision, preparation and organization of work)
Year 2010 E/I Construction Rep.
SPIE ANGOLA
Unit chloration revamping
Precommissioning and commissioning assistance
New Davitt life boat installation.
Precommissioning and commissioning assistance
Since August 2009 E/I Construction Rep. on BLOC 3, ANGOLA SONANGOL PP
SPIE ANGOLA
E/I Construction Rep.
Task performed:
RLO/ROC (Réunion Lancement d’Opération) Preparation and coordination E/I work.
Risk assessment, Task plan and execution.
-Cubicles Marshaling installation and connection
-Connection and shunt-Down for transformer
-Reporting and weekly follow-up
-Precom follow-up and task sheet dossier (documentation,
-Start-up phase
Logistical responsible of Team composed by 15 pax ( Local & Expat). Workpermit preparation, follow-up and coordination.
Since May 2008 E/I Construction Rep. on DALIA FPSO TOTAL E&P ANGOLA
SPIE ANGOLA
E/I Construction Rep. on VISCO Project.
Task performed:
RLO/ROC (Réunion Lancement d’Opération) Preparation and coordination E/I work.
Risk assessment, Task plan and execution.
-Cubicles Marshaling installation and connection
-Connection and Shut-Down preparation for BUS bar connection
-Reporting and weekly follow-up
-Laboratory installation
-Precom follow-up and task sheet dossier (documentation,
-Start-up phase
Logistical responsible of Team composed by 15 pax ( Local & Expat). Workpermit preparation, follow-up and coordination.
Jan 2008 to May E/I Service line assistant manager
SPIE NIGERIA LIMITED
Respond to tenders, place orders, purchases
Management the E/I team.
Client visit on site to coordinate & plan activities.
Dec 2005 to 2007 E/I Construction Rep. on ROSA FPSO Girassol TOTAL E&P ANGOLA
SPIE ANGOLA
Revamping, hook-up & Integration ROSA project
Supervision, preparation and organization of work
Logistical responsible of Team composed by 15 pax ( Local & Expat). Workpermit preparation, follow-up and coordination.
May 2000 to 2005 Industrial electrician
SYLENE Company in Chambéry (Savoie)
Cabinets connection, installation, commissioning & start-up.
Maintenance on site
- July 2003: SPIE CAPAG facilities in Algeria:
Pump Commissioning and maintenance, subcontracted by FLOWSERVE
- March to July 2002: Supervision, assembly, installation and commissioning of E/I equipment on drinking water pumping stations, subcontracted by TEC INTERNATIONAL company, in Eritrea.
- Sept to Nov 2001: PETROGAL RAFINERIE DE SINES: Integration of a cabinet subcontracted by the company DRESSER RAND, on site in Portugal.
Aug 1999 to 2000 Maintenance manager assist.
SICAMEN BOURGOGNE, Beaudrières
Automate, hydraulic, electrical maintenance in charge
-Incubator, hatcher, vaccination
Diploma - Education
1995/1996 Industrial Technologies DEUG degree program, firs
Mes compétences :
Pétrochimie