2009 - 2011The NH90 development and production lead-in is facing the challenge of putting timescales and expenses under control, to face customer commitments as well as preserving project profitability.
Head of P&C for spain NH90 engineering:
- prepare and update NH90 engineering resource planning;
- enter and monitor development master schedule with key milestones;
- define the cost break-down structure according to task definition and delegation;
- allocate development budget to all contributors in agreement;
- propose and organise necessary corrective actions in case of drift risks;
- maintain the Cost-at-Completion forecast and to provide elements to report on the development progress;
- lead the risk and opportunity management process;
- Manage cost planning and controlling with all project managers
- Manage P&C controllers in Eurocopter Spain and Germany;
...
DCNS
- Project Management système d'information
Paris2007 - 2009
Coordination activités des responsables de lot technique,ingénieur qualité projet, maîtrise produit.
Domaine de responsabilités vis-à-vis de la Direction, des
partenaires commerciaux, industriels et du client.
Un schéma de management qui a pour enjeu permanent, la tenue des objectifs de coûts, et de délais du projet.
DECATHLON direction des marques internationales
- Directeur opérations
2000 - 2007Accompagnement du processus de lancement du site et de suivi de mise en oeuvre des différentes infrastructures (AMOA);
Suivi permanent des réalisations sur site (MOE)
Management projet pour rédaction des cahiers des charges, lancement des procédures d’achat et interface fournisseurs, reporting (coût, délais)et suivi qualité