SAIPEM-SA
- Electrical Superintendent
Montigny-le-Bretonneux
2010 - maintenant
-
ETDE DI - BOUYGUES CONSTRUCTION
- Ingenieur Contrat/Planning/Coordination
2009 - 2010
December 2009 : Projet THT - Ingénieur contrat
-
ETDE DI/ BOUYGUES CONSTRUCTION
- Project manager
2008 - 2009
Project Manager (Ventilation, Fire Detection and Protection on the subway in Santo Domingo)
December 2007: Project management of the project and local subsidiary with an average number of (2 expatriates, 6 administrative people and 45 local workers)
• Ventilation :
Mechanical and electrical installation (civil works excluded) of 11 extraction units inside tunnel with for each extraction units:
2 air fans for the mechanical extraction of the tunnel (with variable speed drives with for each fan a nominal air flow of 200000 m3/h and a total pressure of 680Pa.
Temperature, humidity and air flow sensors, lighting, earthing protection.
Acoustic treatment
Communication loop via fiber optic to the SCADA.
• Fire Detection
Complete installation of the fire detection of the 16 stations, control room building (4floors), maintenance workshop, diesel emergency room building and substations.
• Fire Protection
Complete installation of the fire protection network of the workshop area and control room building (fire pumps, piping, sprinklers…)
-
SAIPEM SA
- Ingénieur Electricité
Montigny-le-Bretonneux
2002 - 2007
WORK EXPERIENCE
September 2006: Lead discipline on BRASS LNG U&O Project (BID). NIGERIA
• Reading, checking and validation of projects documents (Specifications, datasheets…)
• Issue of MTO of main & secondary equipment
• Follow up of the project as lead discipline
August 2005: Chief electrical COMMISSIONING Engineer on GUANGDONG Project CHINA
• Redaction of electrical procedures for commissioning.
• Tests, Troubleshooting, validations of procedures and start up of the whole plant
• Set up of LV and HV protective relays.
• Management of a mix team (Filipino and Chinese) - (technical and safety points)
October 2004: Zeebrugge Project BELGIUM
• Design of slab heating system of LNG tank.
• Power balance and consumer list.
• Technical Bid Evaluation(Transformer/Heating System)
• Issue of Specifications and Requisitions.
June 2003: Guangdong LNG Receiving terminal CHINA
• Creation and updating of power balance.
• Follow up of UPS and battery chargers.
• Mission in Beijing (2 weeks) as electrical supervisor at sub contractor office.
• Issue of transformers datasheets(HTB/HTA et HTA/BT)
• FAT of an autotransformer for Hazira Project
June 2002: YOHO EPC2 Project NIGERIA
• Follow up of Electrical consumers, creation and regularly updating of power balance (load study).
• Follow up of Navigational aids package.
• Follow up of UPS and battery chargers.
• Factory Acceptance Tests (FAT) of UPS and battery chargers.
• FAT of 4.16kV switchgear and two 480V Motor Control Centre.
• Mission at Appleton GE (Wisconsin) to validate an instrument air compressor.
• Checking of supplier’s documents.
PROJECTS
February – August 2001: AIR LIQUIDE WELDING FRANCE
• Study of the waveforms of a welding power supply by a Digital Signal Processor
April – July 2000: NITRUVID FRANCE
• 50 kW power supply dedicated to a plasma oven
February – June 1999: ESIEE – Amiens FRANCE
• Control / Command of the water level of a tank.
July 1996: EDF-GDF (West Indies) FRANCE
• Work experience