Entreprises

  • Total E&P Angola - Subsea Engineer

    COURBEVOIE 2013 - maintenant Subsea Technical support for PAZFLOR FPSO
    Maintain subsea control system, Organization of subsea operation with ROV for equipment change out , Xtree commissioning,... Interface with subsea contractor FMC.
  • Perenco - Project Engineer

    Paris 2011 - 2012 Development of a produced water treatment package (hydrocyclone & Compact Flotation Unit) for the Emeraude Field in Congo to restart abandoned well.
  • SAIPEM SA - Commissioning Supervisor

    Montigny-le-Bretonneux 2010 - 2009 UTBS Project, Sonatrach, Algeria
    Gas-Oil Separation Plant composed of 3 desalting / stabilisation trains with a total capacity of 300 kbpd + 4 flash gas compressors
    Process Commissioning Leader
    • Preparation of commissioning / start-up execution plan / handover procedures
    • Review factory tests procedures of main equipments and witnessing of the test
    • Preparation of the scope of subcontracting (leak check and N2 purging)
    • Interface with construction for mechanical completion and organization of site activities with subcontractors and vendors
    • Interface with the client for system handover
    • Start-up of fire water system and review safety systems with local authorities (ARH) to get the approbation for oil-in.
    • Operation leader for the start-up of 1 train composed of 2 separators, 2 desalting stage and one stabilisation column with reboiling furnace.
    • Start-up of flash gas compressors.
    • Start-up of Oily water and API treatment, and chemical injection
  • Saudi Arabian Saipem - Pre-commissioning engineer

    2007 - 2009 Precommissioning coordinator for Uthmaniyah Water Supply Station (Aramco Khurais Wips project)
    Revamp control systems of 5 existing GE Frame 5 turbines to Speedtronic Mark VI system.
    New Electrical Substation
    New Control building with new Foxboro and triconex systems
    New Instrument Air system
    Installation of one new GE NP frame 5C turbine to drive a 45 000 GPM @ 1260 ft Sulzer pump
  • SNC-Lavalin / Saipem s.a. - Process engineer

    2006 - 2007 Canaport LNG Project, Engineering phase Montreal office
    HYSYS simulation; Datasheet; Vendor offer review
    HAZOP review