Saipem S.A
- Operation Engineer - Saipem Representative
Montigny-le-Bretonneux
2012 - 2012
Onboard Kizomba B FPSO (Exxon, Block 15, Angola): in charge of relationship with client/platform.
Managing a team of 10 people (including ropaccess, winch operator and deck foreman), carried out the following topside activities:
- HCL pulling
- I-tube extension installation
- Completion of Riser Protection Frame installation
- Preparation for flexible jumper transfer and pulling
-
Saipem s.a.
- Offshore Field Engineer
Montigny-le-Bretonneux
2010 - maintenant
To provide on-site engineering services and technical assistance for construction related activities to the Superintendent or to the Project Engineer assisting in the achievement of project and/or work site objectives, in accordance with the applicable requirements.
- CPLB Crawler
> Critical Crude Project (Exxon Mobil, Nigeria): 20” pipeline installation (20 meters water depth, S-lay) and bridges installation (associated piles hammering & grouting)
- DSV Bar Protector
o Critical Crude Project (Exxon Mobil, Nigeria): Pre-commissioning of pipelines (pigging, hydrotest, survey activities, mattresses installation, metrology, spool and riser installation, …)
- HLV Saipem 3000
> USAN Project (Total, Nigeria): in deepwater (-750 mts): jumpers, manifolds, chains and gravity bases installation; umbilical laying (static and dynamic), FPSO mooring and dynamic umbilical pulling to FPSO.
> Kizomba PAU (Exxon, Angola): installation of two modules of 400 tons on FPSOs Kizomba A and Kizomba B.
> Seth Project (Petrobel, Egypt): deck installation (1100 tons) and first hook-up activities (topside connection, umbilical and subsea spools installation)
- Saipem FDS2 (Field Development Ship)
> USAN Project (Total, Nigeria): Initiation and laying of 8" gas injection flow line in deepwater (750 meters, J-lay)
-
Saipem s.a.
- Material Coordinator
Montigny-le-Bretonneux
2009 - 2010
Based in Saipem yard in Port Harcourt, Nigeria.
Working on USAN Project (Total, 2 b$), in SCNL Project Management team (Saipem Contracting Nigeria Limited):
- In charge of the Material Control team (8-10 people) in Saipem yard in Nigeria for USAN Project.
- Interface with engineering departement, procurement, post-procurement , transit, project management, QA/QC, welding departement and fabrication team regarding all the material coming on yard for USAN fabrication.
- Interface from the yard with Paris offices to check and coordinate the arrival of material in Saipem yard in Nigeria (transit, certificats, storage, clarification if required about the material received.
-
Saipem
- Trainee Naval Architect
Montigny-le-Bretonneux
2009 - 2009
Final year internship in SAIPEM, on FDS 2 Project (Pipelay vessel): writing of the specification of the onboard stability software. This intership took place on the Samsung Heavy Industry (SHI) shipyard, in Gyeongnam, South Korea
-
GazTransport & Technigaz
- Trainee
2008 - 2008
Technical student internship at GazTransport & Technigaz, in the liquid motion group: study of the variability of impact pressure in LNG carrier tank using a PIV system and a high speed camera.
Reference : Frederic LORMIER (perso.flormier@gtt.fr, dir : (33) 130.234.708)