Benoit LACAVE

Pasadena

En résumé

Pas de description

Entreprises

  • Jacobs - Piping Lead

    Pasadena 2009 - 2010 Piping Lead Engineer on the revamping project of the Terminal Méthanier de Montoir de Bretagne, ELENGY GDF-Suez
    - Responsible of the piping studies for the 2010 revamping: cryogenic supports replacement, valves replacement, new units
    - Piping and insulation project contracts: technical selection and follow up
    - Field enginering: technical solutions to construction problems
    - Preparing the PED (European Pressure Equipment Directive) files
  • Jacobs - Piping Lead

    Pasadena 2008 - 2009 Piping Lead Engineer on the project INEOS S5-TGT, sulfur recovery unit
    - Responsible of the piping studies: coordination of the design team (3Dmodel in PDMS), stress analysis and material management, preparation of the technical proposal , piping work description for the piping contractor
    - Workshare with the Mumbay Jacobs office
  • Jacobs - Piping Lead

    Pasadena 2006 - 2008 Piping Lead Engineer on the Air Liquide, Pergen Project, The Netherland – Cogeneration project inside the Pernis Shell Refinery near Rotterdam

    Field Engineering (Pernis, the Netherlands) :
    - Interface with the Piping Contractor
    - Technical solutions to construction problems
    - Pre-commissiniong phase: steam blowing and chemical cleaning preparation
    - PED certification lead

    Responsible for the end of the detailed engineering in the Paris office :
    - Coordination of the design team, stress analysis and material management
  • AmecSpie Oil & Gas for Technip - Planning Engineer

    2004 - 2006 Offshore Gas Compression Complex – East Area Project, Nigeria,

    Malaysia, England, South Korea, Nigeria

    - Initiated the the job cards workflow: material identification and inventories, compilation of the hook-up and offshore installation drawings, manpower estimation.
    - Issued the hook-up and commissioning planning
    - Led the offshore planning team (2 people). Setup database for progress report: Daily reporting, recording and processing manhours
    - Provided day-to-day support to the Hook-up Manager on various issues
  • Ipedex Production - Procurement Coordinator

    2004 - 2004 South Pars Phase One Project (SPP1), U.A.E

    - Launched the procurement of two years spare parts after SPP1 start-up. Negotiated with vendors. Work included budget presentations to the client
    - Assisted developing procurement software to issue purchase orders (from site request to delivery note) and weekly status report
  • Ipedex Production - Commissioning Engineer

    2003 - 2004 Offshore Gas Production Complex –South Pars Phase One (SPP1), Iran,

    - Maintained and updated the IPCIS database (software to monitor pre-commissioning and commissioning activities).
    - Coordinated the punch lists. Carried out weekly reporting: commissioning activities, punch lists, progress
    - Final documentation
    - Provided IT and technical engineering support. Trained the commissioning engineers to use the IPCIS software
  • Ipedex Production - Process Engineer

    2002 - 2002 Onshore Oil Production Facilities – TOTAL, East Shabwa, Yemen

    - Evaluated, designed and followed up the minor modifications on the plant. Performed a PID check. Organized the PIDs update
    - Assisted supervision during commissioning and start-up of a remote Control Process Unit.

Formations

  • University Of Durban (Durban)

    Durban 2000 - 2001 Chemical Engineering – Process Control

    Postgrade student

    Research on the development of a new mathematical model for a rotary sugar dryer. Objective: Improvement of the sugar moisture control. Performed test campaigns to collect data. Implementation of the model on site. Sponsored by Tongaat-Hulett
  • ENSIACET

    Toulouse 1997 - 2000