Menu

Chabane GUERNINE

Saint-Denis

En résumé

Over 17 years work experience in various Electrical and Instrumentation installation construction, pre- commissioning, commissioning and start-up in O&G, nuclear and energy projects. 12 years in commissioning, 3 years as designer and 2 years erection as E&I superintendent.
- Very large Experience in commissioning and start-up
- Good skills in electrical engineering
- Good knowledge of electrical international standards relative to oil & gas industry.
- Ability to work in a multicultural team.

Electrical Engineer with a good overseas experience in commissioning, precommissioning, construction, and electrical engineering, in a wide range of industry, oil and gas, power station,


During my career I become expert in electrical equipment’s very good understanding of instrument systems and good approach for piping and mechanical issues.

I have gained exceptional skills in developing a close relationship with co-workers as well as a strong ability to communicate, motivate, and guide them in their jobs

Closing the punch lists and warranty of projects and negotiation of no contractual pending points.

Ability to work in a multicultural team.

Mes compétences :
Commissioning
Ingénierie
Construction
Uninterruptible Power Supply
Fire Protection
SCADA
Project Management
Programmable Logic Controller
Primary and secondary testing
Microsoft Office
High Voltage
Fire & Gas
Digital Cross-Connect
Data sheet preparation
Client Assistance and training
Cathodic Protection
Autocad
Siemens Hardware

Entreprises

  • Siemens - Résponsable maintenance centrale électrique

    Saint-Denis maintenant ·Rédaction des procédures d’intervention
    ·Vérification des permis des travaux
    ·Élaboration d’une base de données de la maintenance des systèmes selon les
    documents fournisseurs
    ·S’assurer de la qualité, quantité et de la disponibilité pièces de rechange .
    ·Diagnostiquer toutes les anomalies et déclenchement des turbines
  • Assystem EOS/EDF - Ingenieur essais

    2017 - maintenant EPR Flamanville
    Ingenieur systèmes
    Ingenieur mise en service systèmes ventilation et traitement des effluents
  • EDF - Chargé essais

    Paris 2016 - 2016 Chargé essais électrique centrale Cordemais NANTEs
  • Saipem - Ingénieur commissioning

    Montigny-le-Bretonneux 2015 - 2016 Rédaction procedure commissioning et démarrage FPSO
  • Technip - Electrical superintendent

    Paris 2012 - 2014 Diriger et organiser les sous traitant pour la realisation d'une extension d'une raffinerie
  • TECHNIP - Superintendant

    Paris 2012 - 2014 Projet: EPCC Réhabilitation et adaptation raffinerie (Algérie)
    Activités:
    Gestion des entreprises sous traitantes du montage et réalisation des travaux électriques et instrumentations. Avec une équipe de 04 superviseurs. Nous dirigeons une équipe de 10 superviseurs des travaux client.
    * Responsable du département construction E/I ;
    * Installation des équipements électriques (GIS, tableaux HT/BT, Chemins de câbles, Protections cathodique....etc.)
    * Contrôler la qualité des travaux selon les spécifications du projet
    * Coordonnées et planifier les travaux avec les autres disciplines
    * Rédiger les rapports d'avancement aux responsable construction.
    * Coordonner les modifications site avec le bureau des études
    * Organisation des réunions avec les sous-traitants ;
    * Validation des MAR (Material approval request)
  • SAIPEM SCA - Electrical design engineer

    2011 - 2012 Function : Design
    * Cable sizing
    * One line diagram conception
    * Data sheet preparation ;
    * Following documents vendors ;
  • SAIPEM - Ingénieur électricité de conception

    Montigny-le-Bretonneux 2011 - 2012 Projet: Bureau d'étude
    Activités
    * Conception des schemas unifilaires
    * Schémas logiques des armoires BT/HT
    * Schémas typiques BT/HT pour les vendeurs
    * Revue des documents vendeurs ;
    * Elaboration des schemas d'interconnexions.
  • SAIPEM SCA - Commissioning Engineer

    2009 - 2011 Project : Power station 2x271 Mw
    Post : Commissioning Engineer
    Function : Assistance to project closing
    * Performance tests
    * Closing of pending points ;
    * Preparation of final documentation ;
  • Saipem - Ingenieur commissioning

    Montigny-le-Bretonneux 2009 - 2012 Commissioning et demarrage des systémes electrique (Centrale 2*270 Mw)
  • SAIPEM sa - Ingénieur commissioning

    2009 - 2011 Project: EPCC Centrale électrique 2x271 Mw (Turbines Siemens) (Algérie)
    Activités :
    Gestion de la phase de garantie du projet et transfert de l'usine au client

    * Gestion des appels en garantie client
    * Tests performance des turbines.
    * Assistance aux opérateurs.
    * Traitements de la liste des réserves.
    * Mise à jour de la documentation finale.
  • Saipem - Ingenieur commissioning

    Montigny-le-Bretonneux 2009 - 2012 ·Mise en place d’un planning avec les priorités selon le proceder
    ·Améliorations des solutions et des procédures opérationnelles
    ·Planification et coordination des travaux dans des délais serrés
    ·Préparation des interfaces avec les package des vendeur
    ·Exécution des procédures d'essai;
    ·Étude des problèmes, de diagnostic et de réparation des défauts
    ·Assurer la liaison avec l'installation / ingénieurs de projet
    ·Superviser l'ingénierie et du personnel technique
    ·Rédaction de rapports et de documentation
    ·Fournir un soutien technique
    ·Assurer la sécurité des conditions de travail
    ·Suivie de la période de garantie et levée des réserves
  • Sofregaz - Engineer

    2008 - 2008 Project : LNG Terminal
    Post : Engineer system
    Function :
    * Test, commissioning and start up of fire fighting ;
  • SOFREGAZ - Ingénieur système

    2008 - 2009 Projet: EPCC Terminal LNG Fos sur Mer
    Activités:
    * Test et mise en service .du systèmes lutte incendie
  • Sofregaz (APMS) - Ingénieur systéme

    2008 - 2009 Méthanier FOS/MER Marseille FRANCE
    Mise en service des systémes lutte incendie
  • Siemens O&M - Engineer electricity

    2008 - 2008 Project : Exploitation power plant 2x270 MW
    Post : Engineer electricity
    Function :
    * Development of an electric plan of maintenance Computer-assisted ;
    * Revision of the diagrams and handbooks of maintenance after manufacturer As-built. ;
    * Management of spare parts ;
  • SIEMENS - Responsable maintenance électrique

    Saint-Denis 2008 - 2008 Project : Exploitation et maintenance station électrique 2x270 MW
    Activités:
    Gestion de la maintenance préventive et curative des systèmes électriques.
    * Rédaction des standards des fiches d'intervention. ;
    * Organisation, planification et coordination avec l'exploitation des intervention.de maintenance
    * Assurer le suivi et la commande du stockage des pièces de rechanges.
    * Diagnostiquer les déclenchements
    * Elaboration des fiches de suivies.
  • SAS SAIPEM - Superintendant

    2007 - 2008 Project: EPCC 4 Stations de pompage d'eau
    Activities:
    En collaboration avec le chef commissioning. Gérer les tests de pré-commissioning et commissioning des équipements électriques. Planifier les interventions des fournisseurs.

    * Suivie et compilation des dossiers commissioning. ;
    * Gestion et validation des essais effectués par les sous-traitants.
    * Planification et validation des essais effectués par les fournisseurs.
  • SAS - Engineer commissioning

    PORT-LOUIS 2007 - 2008 Project : Water injection pump station WIPS
    Post : Engineer commissioning
    Function :
    * To follow plan and organize the teams of tests commissioning and pre-commissioning ;
    * To plan and manage according to the progression the arrival of the vendors for the packages ;
  • Saipem - Commissioning electrical engineer

    Montigny-le-Bretonneux 2006 - 2007 Project : Commissioning for two turbines 2x270Mw
    Post : Electrical lead for commissioning and
    management of 4 electrical engineers
    Function :
    * Planning and managing pre-commissioning commissioning tests and starting following electrical systems ;
    * Interface central with item 220 Kv
    * Power transformers.
    * Circuit breakers 16 Kv and MT 6,6 Kv
    * MT delivery system 6.6 Kv
    * Rectifier, inverters and batteries ;
    * 4x1.6 Mw emergency diesels for emergency and black starts, Load shearing ;
    * Loops tests to DCS
    * Interlocks between MV and HV ;
  • SAIPEM-sa - Responsable planification et exécution des tests

    2006 - 2007 Fonction: Electrical commissioning lead
    Project: EPCC Centrale électrique 2x271 Mw et adaptation d'un poste blindé 220Kv(Algérie)
    Activités:

    Responsable planification et exécution des tests et mise en service des systèmes suivants :
    * Poste blindé 220 KV.
    * Transformations de puissance 16Kv/220 Kv.
    * Armoires électriques 6.6 Kv. ;
    * Gestion des interventions des fournisseurs. ;
    * UPS et batteries. ;
    * 4 x 1.6 MW diesels de secours (Black start, Load sharing). ;
    * Mise en service du système F&G. ;
    * Assistance au commissiong et démarrage des turbines. ;
    * Pompes incendie et systèmes de déluge
    * Modification de schémas et leurs mises à jour.
  • Saipem - Superviseur commssioning et start up

    Montigny-le-Bretonneux 2006 - 2009 Commissioning et mise en service des utilités de deux turbines 270 MW de Siemens
  • GEIE Spie Capag Saipem - Commissioning engineer

    2005 - 2006 Project : OZ2 Six Fuel pumps stations
    Post : Commissioning engineer
    Activity : Management of Warranty period and
    Pending pinch list items.
    * Diagnostic of troubleshooting and delimitation of the responsibilities. ;
    * Order defective material and replacement.
    * Draw up reports towards ;
  • GEIE Spie Capag Saipem - Deputy manager commissioning

    2004 - 2005 Project : OZ2 project phase2
    Post : Deputy manager commissioning and
    Start up responsible for electrical and instrumentation systems

    Main activities :
    * HV panels 30 Kv
    * MV panels 5,5 Kv
    * LV switchboards and MCC's
    * power Transformers
    * Rectifier, inverter and set of batteries
    * Systems ESD
    * Fire protection System. ;
    * Configuration and start up of motorized valves ;
    * Client Assistance and training. ;
  • GEIE Spie capag Saipem - Commissioning supervisor

    2003 - 2004 Project: OZ2 phase1 pumping station.
    activity : E/I Commissioning supervisor
  • GEIE Spie Capag - Commissioning engineer

    2003 - 2006 Projet: EPCC OZ2 Six stations de pompage pétrole et un terminal (Algérie)
    Activités:
    * Suivie de la période de garantie
    * Diagnostiquer et maintenance curative ;
    * Commissioning et mise en service des armoires HT/BT 60 KV/30kv/5.5 KV ;
    * Mise en service des MCC HT et BT ;
    * Mise en service des transformateurs de puissance ;
    * Commissioning du système ESD ;
    * Mise en service des pompes incendie et détection F&G. ;
    * Configuration des vannes motorisées
    * Assistance de mise en service du DCS ;
  • NUOVO - Electrical supervisor

    2003 - 2003 Project: Power station 1X110 Mw
    110MW.
  • GEIE - Ingenieur commissioning

    2003 - 2006 Mise en service de six stations de pompage (Algérie)
    ·Pré-commissioning, commissioning et démarrage des systèmes électrique
    ·Paramétrage et tests des protection HT/MT et BT
    ·Contrôle et mise en service des armoires HT/MT et BT
    ·Tests des boucles et des différentes interfaces
    ·Mise en service des UPS
    ·Tests des équipements instrumentation.
    ·Mise e service des automatismes de fonctionnement ainsi que des sécurité et des Emergency shut downs
    ·Supervision des équipes pendant les manœuvres de mise en service
    ·Tests et mises en services des systèmes de détection et lutte incendie
    ·Levée des réserves et suivie de la période de garantie
    ·Assistance aux opérateurs
    ·Rapports avec l’ingénierie pour la correction des anomalies ou amélioration du systéme
  • NUOVO - Commissioning supervisor

    2002 - 2003 Project: Power station 3X110 MW (Hassi-Berkine)
  • NUOVOPIGNONE - Superviseur chantier

    2002 - 2003 Fonction: Superviseur chantier électricité (Commissioning)
    Projet: EPCC centrale électrique 3x110 Mw (Algérie)
    Activités :
    Test pre-commissioning et commissioning des équipements électriques
  • ANSALDO Energia - Commissioning supervisor

    2001 - 2002 Project: Power station of 02X239MW.
    Activity: Electrical supervisor commissioning


    * French: Very good
    * Arabic: good.
  • ANSALDO ENERGIA - Superviseur chantier

    2001 - 2002 Fonction: Superviseur chantier électricité (Commissioning)
    Projet: EPCC centrale électrique 2x240 Mw (Algérie)

Formations

  • Université Sciences Exactes (Tizi Ouzou)

    Tizi Ouzou 1989 - 1995 Ingénieur d'état en électrotechnique
  • Université Des Sciences Exactes Et De La Téchnologie UNIVERSITAIRE (Blida)

    Blida 1988 - 1994 INGENIEUR

    These ingéniorat Mentien Trés bien
  • LTD De Dellys (Boumerdes)

    Boumerdes 1986 - 1989 Bac professionnel en électrotechnique mention assez bien

Réseau

Annuaire des membres :