Paris2007 - maintenantClient: British Petroleum
Programme: Backbone
Duration: 03/11 - Actual
Location: Stockley Park - UK
Role: Training Lead
Client: European Space Agency
Programme: FINREF
Duration: 11/10 - 03/11
Location: Nordwijck (Hollande), Rome (Italie) et Paris (France)
Role: Organisation Readiness Lead
Client: EDF Energy
Programme: Orchard
Duration: 11/2007 - 06/2010
Location: London - UK
Role: ISU/PM/CS Functional Consultant (11/2007 - 06/2009) and Training Lead (07/2009 - 06/2010)
Project: Buy Bill Collect
Duration: 1 month (01/2008 - 02/2008)
Location: Exeter - UK
Role: Business Consulting
Client: Transmission System Operator (EirGrid & SONI)
Programme: Single Electricity Market Program
Duration : 10 months (01/2007 - 10/2007)
Location: Dublin - Ireland
Role: Business Consulting and Test Lead
Capgemini
- Functional Consultant SAP IS-U
SURESNES2004 - 2006Mission/Client: implementation of SAP IS-U to enable the GRD (gas network distribution) to bill others gas suppliers
Project: OMEGA
Duration: 3 months (10/2006 - 12/2006)
Location: Paris - France
Main tasks:
- Carry out the Unit Testing phase
- Perform the Integrated testing phase (Meter reading / Billing / Invoicing / FICA area)
- Invoicing and settlement (FICA)
Mission/Client: implementation of SAP-IS-U / CRM (version 4.72) to enable the O.N.E to bill professional and domestic customers
Project: SIRIUS
Duration: 12 months (10/2005 - 09/2006)
Location: Casablanca - Morocco
Main tasks:
Managed three person in the invoicing team: two technical consultant and one key user
Led the Billing / Invoicing team to perform the following activities:
- Gather and analyse the client needs in the Billing / Invoicing area
- Organise design workshops
- Prepare of functional specifications
- Supervise developments in the Billing / Invoicing area
- Carry out the Unit Testing phase
- Perform the Integrated testing phase (Billing / Invoicing area)
Mission/Client: implementation of SAP-IS-U (version 4.64) to enable Gaz de France to bill for professional customers in the Deregulated Market
Project: SGC-NR & RAPSODIE TMA
Duration: 17 months (05/2004 - 09/2005)
Location: Paris - France
Main tasks:
Captured and processed end-users requests and issues:
- Resolution of the demand thanks to a functional solution or to customizing setting
- Completion of scenario, integrated and regression tests
After go-live: post-production support on the Gas solution
SD / IS-U integration:
- Unit testing and integrated testing of SD / IS-U integration
- Integration of SD invoices within IS-U mass-invoicing
- Ensured correct postings to FI/CA
ECL - France (Group Péchiney-Alcan) - Lille
- Key User SAP SD (version 4.6C)
2003 - 2004Mission/Client : SAP-R3 (version 4.6C) implementation at ECL - France
Project : CONTACT
Duration: 8 months (10/2003 - 05/2004)
Location: Lille - France
Main tasks:
Testing phase: Designed and ran test cases on Sales processes and worked on the integration with modules: PS (project), PP (manufacture with the order), FI (countable charges), CO (controlling), MM (product management)
SD change management:
- Definition of training scope
- Definition of end-user training profiles
- Preparation of user manuals and user training deliveries
- Carried out end-user training (course to 20 person)
After go-live:
- Post-production support to the end-users
- Post-production Change Requests management: identification, analysis, approval and handover of CRs to SAP consultants