I Provide the Commissioning & Start-up Management & Services of EPCC projects from the project tender stage, through the design stage, procurement, construction, commissioning, start-up and up to normal routine production/operation of the installation as described hereafter. I provide also Services during Shutdown & Turnaround activities/phases.

Specialties
Construction, Commissioning, Start-Up, Operation

Mes compétences :
Start up Leader
Commissioning Site Leader
Commissioning System Leader
Commissioning SPDT

Entreprises

  • Total - Oil Loading Terminal Commissioning Site Leader_FPSO CLOV Project

    COURBEVOIE 2014 - 2015 Click to edit position descriptionOnshore (LOBITO) & Offshore Phase ( FPSO CLOV):
     Prepare, direct and manage the Commissioning & Start-up of the Buoy.
     Focus point and main interface between construction, commissioning and operations to perform close out meeting with all concern parties in presence of B.V prior to sign the OT steps and OTC (operation test Certificate).
     Acknowledge and validate all Pre-com & Commissioning dossiers
  • Total - Utilities system leader (FPSO CLOV Project in Angola)

    COURBEVOIE 2013 - 2014 Click to edit position description Prepare / check / approve OTP of different sub-systems of the new facilities (Air compressor packges, Cooling system, Hot water circulation, gas turbine, Fire Fighting System....etc).
     Follow all activities progress / punch items / systems completion via ICAPS.
     To follow the schedule of commissioning of systems in order to reach the planned end date
     Prepare, direct and manage the Commissioning activities of all utilities including machineries start up.
  • Yemen LNG - Commissioning Site Leader (• Yemen LNG Up stream project (Phase 2)

    2012 - 2013  Prepare, direct and manage the Start-up of Yemen LNG Upstream facilities.
  • Yemen LNG - Commissioning & Start up Manager

    2011 - 2012  Prepare, direct and manage the Start-up of Yemen LNG Upstream facilities.
     Process engineering for this project: Follow up the HAZID, HAZOP, details engineering.
     Working with the Projects Managers towards aligning projects and operations objectives.
     Facilitated the Interface between Operations ,PMT. EPC.
     Provided Operational input into our FEED and Detailed Design EPC contractors documentation and design reviews.
     Managing commissioning man powers and Vendors mobilization to site.
     Commented / approved of all pre-commissioning / Commissioning dossiers and send to site for implementation.
     Commented / approved of all start up Procedures for site implementation.
     Commented / Approved plant operating manual and issued to site.
     Commented / Approved of all GENP & SOLAR site acceptance test procedures.
     Reviewed / compiled all comments issued by PTR-4 (Project Technical Review).
     Follow up all LPO (Local Purchase Order) related to the project
  • Qatar Gas LNG Onshore Plant - Utilities Superintendent

    2010 - 2010  Pre commissioning /Commissioning Utilities Superintendent in Qatar Gas LNG onshore Plant (Train 6 and 7).CTJV Project, Raslaffan Industrial City, Qatar.
     Prepare / check / approve Method of statement of different sub-systems of the new facilities (Water flushing, Air blowing, Steam blowing, Solo Run, Mechanical run, etc).
     Follow all activities progress / punch items / systems completion via WIN-PCS.
     To follow the schedule of commissioning of systems in order to reach the planned end date
     Prepare, direct and manage the Commissioning activities of all utilities including machineries start up.
     Commissioning of (Macchi Italy) VHP Boiler 220 Ton/Hour.
     Hydro milling of Pipe and Vessel.
     Cooling Water Mechanical Cleaning and Passivation.
     Start-up of Steam Turbine Pump.
     Commissioning of Gas Turbine Generator.
     Commissioning of Steam Turbine Generator
     Manage the start-up of new facilities (hydrocarbon feed-in, rotating machines, testing of safety systems, performance test of process units)
  • TOTAL - Start up leader (TOTAL E&P Indonesie) TUNU North Phase 11 & 12 facilities

    COURBEVOIE 2008 - 2009  To prepare, direct and manage the Start-up of TUNU North Phase 11 & 12 facilities.
     Prepare the start-up of the different sub-systems of the new facilities (start-up procedures, Operguide Procedure, Job Risk Assessments, process inerting, etc …).
     Prepare Plant Performance Test Procedure.
     Focus point and main interface between construction, commissioning and operations for TUNU North Phase 11.
     Receive new installations on behalf of AMT, check that new installations are in line with statement of requirement and meet requirements of operations division in terms of safety and operability.
     Approve all RFSU dossiers & installation.
     Identify with concerned site staff the training for operation/maintenanace site personnel.
     Perform Weekly and Monthly Reports about all activities including construction & commissioning with the recommendation to improve quality / safety of work and to improve the production
  • Total - Start up Coordinator (TOTAL E&P Indonesia) SiSi nubi Field Phase one

    COURBEVOIE 2007 - 2007  Participate on the preparation of start-up procedures.
     Follow-up of specific Commissioning activities (Leak Testing, OTPs, etc..).
     To co-ordinate the production start-up of Sisi Nubi phase 1 facilities to ensure a safe and timely start-up of the new facilities.
     Follow-up and coordinate all start-up related activities of new facilities, including troubleshooting.
     Provide operational experience, to be shared with the Sisi Nubi production operations team
  • Total - Technical Support for Start-up (FPSO DALIA PROJECT in Angola)

    COURBEVOIE 2006 - 2007 • TOTAL E&P Angola FPSO DALIA (240,000 BBLs/Day).

     Pau & Site: Prepare initial start up procedure / sequence using Total Operating Guide.
     Assist the Operational Test Procedures (OTP’s) with Vendor.
     To follow up/report all process systems progress and punch list clearance.
     To follow the schedule of commissioning of systems in order to reach the planned end date.