Menu

Emmanuel GUILLEMARD

PARIS

En résumé

Pas de description

Entreprises

  • SUBSEA 7 (ex Acergy) - Project Engineering Manager

    2002 - maintenant SUBSEA 7 is a leading offshore contractor to the oil and gas industry, specialising in technologically sophisticated deepwater engineering, flowline and pipeline lay, construction, inspection and maintenance services. The Company operates in Europe, the Middle East, West Africa, Asia Pacific, and the Americas

    2014 - Actual -> Project Engineering Manager - SUBSEA 7, Paris
    Major SURF EPCI Project Bidding

    2012 - 2014 -> Project Engineering Manager - SUBSEA 7, Paris
    CLOV (TOTAL - Angola)
    Project Engineering Manager for design engineering activities : Risers, Flowlines, Structures, Subsea Equipment.

    2010 – 2012 -> Lead Engineer – SUBSEA 7, Paris
    CLOV (TOTAL - Angola)
    Lead Engineer for detailed design of Hybrid Riser Tower (HRT), Single Hybrid Riser (SHR), Flexible pipes and Subsea Arches: hydrodynamic analyses, interferences, structural analyses.

    2007 – 2010 -> Lead Engineer – ACERGY, Paris
    AB15 GAS GATHERING PROJECT (EXXON - Angola)
    Lead Engineer for detailed design of Subsea Manifold: piping analyses, structural analyses, equipment and subsea control system definition and procurement follow up, fabrication follow up and testing follow up.

    2005 – 2007 -> Lead Engineer – STOLT OFFHORE and ACERGY, Paris
    GREATER PLUTONIO (BP - Angola)
    Lead Engineer for installation scope of subsea structures: suction piles, subsea manifolds, rigid spools, flying leads and all subsea connections (MATIS, CAT). Procedure of installation preparation, installation analyses follow-up, installation aids definition with procurement follow-up, risk assessment preparation and onshore testing procedure preparation. Onshore assignment for structure preparation and offshore assignment for suction pile installation.

    2004 – 2005 -> Project Engineer – STOLT OFFSHORE, Paris
    BENGUELA BELIZE (CHEVRON - Angola)
    Procurement follow-up of subsea connectors (Oil States) – Onshore assignment for rigid spool preparation and offshore assignment for rigid spool installation and connection.

    2004 -> Project Engineer – STOLT OFFSHORE, Paris
    GIRASSOL – Inter-campaign MATIS tie in (TOTAL - Angola)
    Onshore preparation and offshore connection of Girassol new jumper to well connections with MATIS (Modular Advanced Tie-in System).

    2003 -> Field Engineer – STOLT OFFSHORE, Paris
    OGGS SHELL - Nigeria)
    Onshore and offshore operation preparations for an Above Water Tie-In onboard Acergy Orion.

    2002 – 2003 -> Junior Engineer – STOLT OFFSHORE, Paris
    GIRASSOL (TOTAL - Angola)
    Installation procedures of subsea closure recoveries, spool flanged connections (MATIS: Modular Advanced Tie-In System), and spool deployment. Onshore assignment for fabrication follow-up. Offshore assignment for Spool deployment, subsea intervention and subsea connections.

    2002 -> Junior Engineer - SOFRESID (Cril Technology)
    DOLPHIN (Dolphin Energy - Qatar)
    Junior Structural engineer: Design of tripod and jacket structure.

Formations